Title
title
Accept Contract No. 5645 and Order Final Payment to Insituform Technologies, LLC for Construction of District 32 Main Trunk Sewer Rehabilitation (Project); in the Total Amount of $2,999,131.80
end
Summary
body
Summary: The Project consisted of the rehabilitation of approximately 15,341 feet of 15-inch to 21-inch diameter corroded concrete pipe and appurtenant structures. The work was located within the City of Santa Clarita. Two change orders totaling $99,106.05 were approved for this Project.